Road repairs on Pervomaiskaya and Rybnikov in Naryan-Mar are on schedule

During the weekly operational meeting of the governor of the NAO, Yuri Bezdudny, the acting head of the department for construction, housing and communal services, energy and transport, Nikolai Sokolov, spoke about the progress of road works that are being carried out in the region as part of the Safe High-Quality Roads national project.

Photo: Alexandra Kustysheva/nao24.ru

Within the framework of the national project “Safe High-Quality Roads”, this year it is planned to repair roads on Pervomaiskaya and Rybnikov streets in Naryan-Mar, as well as the reconstruction of the road in Ozerny Lane and on Zavodskaya Street. Work on Rybnikov and Pervomaiskaya has already begun.

The weather is fine, but it won’t be like this indefinitely. Contractors need to use this “window” to complete the work as quickly as possible. Execute them well. Because laying asphalt when it rains is pointless. We have already been through this,” Governor of the Nenets Autonomous Okrug Yuri Bezdudny addressed Nikolai Sokolov.

The acting head of the department of construction, housing and communal services, energy and transport of the Nenets Autonomous Okrug said that municipal contracts were concluded for the facilities on Pervomaiskaya and Rybnikov with a deadline of October 1, 2022. The customer is MKU “Clean City”.

On Pervomayskaya Street, the contractor is Kapitalstroy-NAO LLC. On a 1.1 km section, it is necessary to replace the asphalt concrete pavement, partially replace the curb stone, and apply horizontal road markings.

At Rybnikov, the work is carried out by IP Abacharaeva A.Ts. The repair of the 119-meter section includes the replacement of the asphalt concrete pavement and the application of horizontal road markings.

“Now both facilities have completed milling of the pavement, since the beginning of this week, the contractor has begun laying asphalt concrete pavement on Pervomaiskaya Street. The work at the facilities will be completed on time, there are no risks of non-completion of work,” said Nikolai Sokolov.

He also noted that this year, work will start on the reconstruction of roads on Zavodskaya Street and Ozerny Lane. The reconstruction should be completed in 2023.

Works on Ozerny Lane will be carried out by Kapitalstroy-NAO LLC. The length of the repaired section is 760 meters.

The contractor will perform the installation of pavement, sidewalks, lighting, technical means of organizing traffic.

Work on the reconstruction of the highway on Zavodskaya Street will be carried out by JSC Nenets Oil Company. The length of the road section is 1.1 km. Scope of work – installation of pavement, sidewalks, lighting, technical means of organizing traffic.